Is there a way to schedule a begin date on tasks and have an alert sent out? I work in a school. Some of the projects depend on different courses wrapping up. It would be helpful to have a remidner built in as well as the deadline. IE, looking for a way to document when we get the green light to go into a classroom and tear out all the equipment.
Hi Patrick,
Not exactly—you could record dates in a custom field using the Custom Fields Power-Up, but this won't generate notifications. This is informational only.
For what you describe, I would suggest using the Due Date in multiple ways. While you can only specify one due date at a time, you can change that due date and re-use the field. You could initially set the due date to when you plan to get started on the project in order to ensure a notification. Once it starts, you can change the due date to the completion date if you'd like.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.