Hi all
I'd like to have a card on each project board that shows the percent complete of a certain type of card/task. Let's say I have a Label for each phase of my project. I'd like to display a field that tells me the % of all tasks complete across all cards with that label.
I looked at Dashcards but it seems it can only show a count, not a percentage.
Any other way to do this please?
Thanks.
Hi @Dorian
I wish that Dashcards had this too, it would be a great feature...
There are some ways to get this.
Reporting Power-ups
Alternatives
Capture all of your project tasks into a Project card using Checklists and use Show Checklist power-up to show a
Capture all of your project tasks into a "Project Card" using checklists and automation, use custom fields to set Total Tasks, Completed Tasks and %Complete then use a dashcard to display the %Complete custom field