So I believe this is the workflow that's happening:
1. Start sprint
2. Stories are later pulled in that are not estimated
3. Stories are estimated
4. Stories are completed
5. Jira shows - where estimate should be for said completed stories
6. Points are not reflected on velocity though they were completed durint the sprint
Scope was increased and the burndown reflects this when the estimates were entered but the velocity does not show the added work that was completed. Though I agree this should not be added to the intial commitment of the sprint number, it should be counted in the velocity as stories that were finished.
Is this a feature or a bug? If it is a feature, is there any way to turn it off?
Recommended Learning For You
Level up your skills with Atlassian learning
Learning Path
Apply agile practices
Transform how you manage your work with agile practices, including kanban and scrum frameworks.
Learning Path
Configure agile boards for Jira projects
Learn how to create and configure agile Jira boards so you can plan, prioritize, and estimate upcoming work.
Jira Essentials with Agile Mindset
Suitable for beginners, this live instructor-led full-day course will set up your whole team to understand how to use Jira with an agile methodology.