Automatic feature scheduling

Emma May 13, 2025

Hi,

I have a backlog with 9000 elements (solution epics, epics, user stories) and more than 10 teams. I am using Structure, I have a Gantt chart. Is there a possibility to automatically schedule feature in Gantt chart based on rank? What should I configure? 

2 answers

1 accepted

Suggest an answer

Log in or Sign up to answer
0 votes
Answer accepted
Stepan Kholodov _Tempo_
Community Champion
May 13, 2025

Hello @Emma 

It depends on what you want to see as a result and what kind of data you have in your Jira. It's not possible to use only the Rank field for scheduling each issue differently from other issues.
If issues have links between them, then they can be automatically scheduled by the dependencies on the Gantt chart. If there are no dependencies, then you can use the Formula for calculating the Start date for each issue based on its individual parameters. 

If you would be interested, we can look into your configuration in more detail and suggest some options for scheduling. In this case, please reach out to su directly at our support portal.

Best regards,
Stepan
Tempo (the Structure app vendor)

0 votes
Dave Rosenlund _Trundl_
Community Champion
May 13, 2025

Hi, Emma. I moved your post here, to app Central, because this is the best place for questions about Atlassian Marketplace apps. I also added a couple of additional tags to make it clearer that we’re talking about the add-on Structure by Tempo.