Hi Team, Is there a way in Jira Structure Gantt + resource view, to show how much a task was estimated and how much effort actually logged by assignee.
Example:
Current Date: 30Aug2024, UserStory_001 - Estimated 5 days, with start date as 1-Sep-2024
Current Date: 03Sep2024, UserStory_001 - User logged total 3 days effort (1 day effort daily from 1sep to 3rd sep, so total logged effort shown in jira is 3 days)
In this case, is there a possibility to show in Gantt view , how much effort was logged against the estimated period
Also in Resource usage view, can we get view of how much effort was planned on particular day for a resource and how much effort was logged by them
Hello @JK
I answered a similar question in this post of yours: https://community.atlassian.com/t5/App-Central-questions/Jira-Structure-gantt-resource-usage-to-show-logged-efforts-for/qaq-p/2797895#U2827221
This might help.
Best regards,
Stepan
Tempo (the Structure app vendor)
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.