Changing effort per day in Tempo Planner

Rakesh Pradhan
Contributor
July 22, 2024

Hi all 

Is there an elegant way to allocate specific time to a task per day in Tempo Planner 

Scenario

A PM has created a task called Review Technical  Scope and Assigned it to a resource with and estimate of 10 Hours in a 5 day week in JIRA and it is synched with Tempo Planner

Tempo planner will automatically spread the 10 hours across 5 days = 2 hours per day

What i want to do is phase the effort across the 5 days e.g

  • Mon 4 Hours,
  • Tue -2 hours
  • Wed - 1 Hour
  • Thu - 1 hour
  • Fri - 2 Hours

I can split the task into 5 and allocated each segment the effort but i find this very cumbersome to do particularly for tasks which take longer 

Any ideas welcome

Perhaps a feature change could be introduced that can model the daily distribution of hours at creation without the need to split tasks 

1 answer

Suggest an answer

Log in or Sign up to answer
1 vote
Valerie Knapp
Community Champion
July 22, 2024

Hi @Rakesh Pradhan , thanks for your question.

I don't know that this is possible yet in Tempo, but BigPicture has a function like this called, 'workload contouring' - https://appfire.atlassian.net/wiki/spaces/DLP/pages/297046379/Workload+contouring 

^ Is this more what you are after?

Rakesh Pradhan
Contributor
July 23, 2024

Thanks Valerie 

We have big picture and have seen the workload contouring feature .  We are trying to use Tempo capacity planner add in to manage resource assignment and allocation as we already have tempo timesheets as our time tracking tool 

 

Like Valerie Knapp likes this