Tempo Time Spent not aggregating from sub-tasks

Andres Oss May 27, 2025

Tempo isn’t currently aggregating Time Spent from sub-tasks.
When we open an Epic, we expect the total to include hours logged on its sub-tasks, its parent tasks, and the Epic itself. Right now, the total is incorrect—it only adds up hours from the Epic and its direct tasks.

We see the same problem in Confluence pages that display Jira issue lists: the Time Spent column doesn’t sum the hours as expected.

2 answers

Suggest an answer

Log in or Sign up to answer
1 vote
Joshua Green May 27, 2025

Yeah, this is a known pain point with Tempo — it’s supposed to roll up time across sub-tasks and parent issues, but often falls short in practice. You're not alone in seeing mismatched totals in both Tempo and Confluence-linked Jira views.

0 votes
Dmitry Astapkovich _Colined_
Atlassian Partner
May 30, 2025

This is one of the biggest reasons we have Pivot Report customers, who using Tempo. 

SCR-20250530-mpmr.png

 

On top of stand alone report, we have two customizable widgets for Issue/Work item view: Issue Tree and Issue Progress. You can define if you want all work items to be calculated for totals, or only so called "leaf nodes":

SCR-20250530-mqty.png



SCR-20250530-mrmy.png

Andres Oss June 4, 2025

It looks good, although it is another extra expense for the Jira setup.
Tempo should inherently have such configuration properties available.