Our site uses BigPicture for detailed project schedules.
Teams would like to also use timeline for a quick visual.
It looks like Timeline doesn't use end date (which our BP is using) but instead uses Due Date.
In this scenario, would the teams manually keep due date in sync with end date so that both BP and Timeline are in sync for epic end dates?