Appreciate it if I can know the difference between the Original estimate and the Time remaining in JIRA.
With admin access, I am still unable to view all the Team mates Log timing. What could be the reason and How can I resolve it
Anupa
5147141122
In case you are referring to a Jira instance without special Apps as for tracking / worklogs then I can confirm that viewing worklogs is not restricted at all. That means everyone can see all worklogs as long as he/she has "Browse Permissions" to the Jira project in question.
Some more information on loggin time on an issue can be found in documentation:
https://support.atlassian.com/jira-software-cloud/docs/log-time-on-an-issue/
Related to that topic is also the complex "estimation on issues" - those information can be found here:
https://support.atlassian.com/jira-software-cloud/docs/estimate-an-issue/
Original estimate (OE) is what you initially scope the work to be. Time remaining = OE - total logged work (unless you manually set the RE at some point when logging work).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.