Hello all,
I am trying to create an automation rule that will periodically create a maintenance task for me with a series of subtasks.
I have a rule that creates a scheduled task for me. This works. But I can't get the subtasks to be created in the same process. So my question is, can I create a task and subtasks scheduled by date in an automation at all or do I have to create two tasks here?
Thanks in advance for the support!
Hi @cDemmerle
This can be achieved using the Branch rule / related issues option in the rule:
Result on 1 execution:
Hopefully this answers your questions,
Regards,
David
Thx Works great and was soo simple i haven`t seen that Option when playing around :-D .
Thx again and have a nice week!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.