Hi all,

 

How do I get additional fields to appear in backlog view for items scheduled in active sprint.  For example, during sprint planning I would like to use backlog view and be able to see the status of the items assigned current sprint.  Note, we plan sprints day or two prior to end of current sprint.

 

Thanks

2 answers

2 accepted

0 votes
Answer accepted
Fabio Racobaldo _Herzum_
Community Champion
July 28, 2022

Hi @Dorothy Callahan ,

you can add field in card layout for active sprints. Btw, on the backlog view you can see the status of items for the current sprint too by default.

Fabio

0 votes
Answer accepted
Dave Mathijs
Community Champion
July 28, 2022

Hi @Dorothy Callahan ,

Via Active sprints, you click on the three dots (...) and go to the Board settings.

From there, click on Card layout.

You can add up to three extra fields for both the Backlog and the Active sprints.

Choose Status as Field Name to add.

Dorothy Callahan
Contributor
July 28, 2022

Thanks so much!  The light bulb went off right after I posted this and figured it out.  I came back to delete question but you beat me to it.  You are quick in the AM.

 

Thanks again.

Like Dave Mathijs likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events