I checked the issue type screen scheme and field configuration scheme. It turned out nothing is unusual. But when I try to create a task, Epic Link is still required. How can I make it an optional field?
Hi @L J and Welcome to Atlassian Community!
By default, the Epic Link field is not required when creating a task. So it's possible that you're being affected by a custom configuration.
I see that you've already checked the Field Configuration Scheme. However, here are some other ways the field might be made required:
Workflow Validator: Check whether there's a validator on the initial step of your workflow.
ScriptRunner Behaviour: It's possible that a behaviour is configured to make the field required.