Hi

I want make a report that show first assignee in a multi assignee project.
may be after issue creating , user 1 assign issue to user 2 promptly, while no comment or progress don't occure in issue.
This report should show user 1.
Is there a field or .. that fill this report?

 

thanks

 

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 6, 2019

You will need to find or write code to do this. 

I would use scriptrunner to write a scripted field that pulls out the initial assignee.