Hello community,
we have a bunch or projects und JWM which are built in the classic gantt way. Means we have Milestones(Tasks) which some sub tasks.
I would like to setup an automation, that when alle the subtasks of a parent issue have the same status(scheduled), that the highets due date from the group of sub tasks is passed to the parent issue.
Can anybody help me on this?
Bests
Olli
Hi @Olli Lutz , here is an earlier post I was involved in for similar request.
Automation-Copy-latest-due-date-value-from-stories-to-epic
the key smart value to leverage is ...
{{issue.subtasks.Due date.max
}}
could you please send us automation steps how to get highest due date from subtasks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.