Hi All,
We have upgraded to Jira Premium recently and added 'Initiative' as an additional level in Issue Types.
If we do a burn up report, will it roll up to an Initiative level? Please let me know if this has worked for you.
Thanks,
Saurab
I am also assuming you are using the Burn Up report that is available in Jira? If this is the case then as far as I know, the Advanced Roadmaps is an add-on which is created by Atlassian but still an add-on. Advanced Roadmaps does provide it's own completion utility in the Plan when you add the Field "Progress" to your view, however, I'm fairly certain that that reporting in Jira (I call it Jira proper) doesn't look for the additional parental linking (up to Initiative) that the Advanced Roadmap program does.
TLDR: Advanced Roadmap utilizes both 'parent link' and 'epic link' and creates a Progress field to show progress in the Plan view. Jira uses 'epic link' and so most likely will not pull in based on 'parent link'.
Thanks Crystelle! My research was leading me to the same inference as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Point of clarification, when you say Jira Premium are you referring to Advanced Roadmaps?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.