Is it possible to change the names of the steps in a project?

Samantha Butler April 26, 2018

As a default my projects have the steps of:

Backlog

Selected for Development

In Progress 

Done

 

Can I ask if these names can be changed?

1 answer

1 accepted

0 votes
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 26, 2018

Do you mean that you can see these names in a board? Is it a Jira Software project? Could make a screenshot?

If it is on a board, you can go to the board configuration and change these steps in the columns menu.

Samantha Butler April 29, 2018

Hi,

Thank you for your reply. Yes, it is in a board. We have software projects and business projects and it shows in both. Please see a screen shot.

Screen Shot 2018-04-30 at 8.11.01 am.png

Samantha Butler April 29, 2018

It is not a huge issue if I cannot change them, we just have some staff who are not informed on JIRA/Project management terminology and they will get confused with backlog etc.

Like Eduardo Carrada likes this
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 29, 2018

For Software, board columns are defined by the config for the board, you can get there by clicking the "configure board" option near the top right of the board (as long as the creator/owner has given you the right to do so)

For Business projects, the board follows the workflow you have defined for the project.  So to change the columns, edit the workflow.

Samantha Butler April 29, 2018

Thank you very much. I have now been able to make changes :)