Moving parent task on completion of sub task using Post function

Martin Kronstrom April 12, 2018

Hi, 

We are using the cloud based version of Jira.

We really want to enable the functionality of moving user stories once the sub tasks are complete. 

We have been to this link:

https://community.atlassian.com/t5/Jira-questions/How-do-I-control-the-Story-status-when-Story-sub-tasks-are/qaq-p/195643

The problem is that the update parent issue does not occur in our instance. Once the last sub task in the story is complete, you have to manually move or transition the story to the sub task statuses. 

Post function also does not show the transition "Transition parent issue"

We see that greenhopper does have the functionality:

https://www.atlassian.com/blog/archives/announcing-greenhopper-5-10-the-best-tool-for-scrum-teams

How do we enable automatic transition of the parent once tasks are complete?

1 answer

0 votes
Deleted user April 12, 2018

Hi @Martin Kronstrom,

I believe there is an answer in a similar question.

However it does require the plugin: JIRA Misc Workflow Extensions

Hope this helps

Martin Kronstrom April 12, 2018

Thanks Danny, I would have liked this as a standard feature, interesting that we have to pay for transitioning functionality. Especially since it formed part of greenhopper initially.

Deleted user April 12, 2018

Completely agree with you Martin

Suggest an answer