Setting the desired date in Due Date field using Automation Rule

sowjanya gondi
Contributor
May 21, 2020

Can somebody please help me with this? 

I am trying to set the Due Date Field to a certain date but it's not working on the issues where due date already exists. Is there a way to set the desired date regardless of prior value? overwrite?

I am using the smart Value {{issue.Sprint.endDate.jiraDate}} for Due Date field.Automation_Due Date.png

 

2 answers

1 vote
John Funk
Community Champion
May 24, 2020

Hi @sowjanya gondi  - Can you give us more information as to what is not working?

Can you share a screenshot of the Audit log for when you run it? 

sowjanya gondi
Contributor
May 25, 2020

Hi John, Thank you for responding. I corrected a couple of things and the rule started working now. 

1. Cleared the pre-existing value in the date field before populating it with a new date. For this step, there was reference available here in Atlassian community

2. Used smart value {{now.plusBusinessDays(10)}} instead of {{issue.Sprint.endDate.jiraDate}}

I am ok now. Thank you.

.  

Like John Funk likes this
John Funk
Community Champion
May 26, 2020

Great! I am glad it is working for you now!

0 votes
sowjanya gondi
Contributor
May 21, 2020

Can somebody please help me with this? Is the question not clear? 

I am trying to set the Due Date Field to a certain date but it's not working on the issues where due date already exists. Is there a way to set the desired date regardless of prior value? overwrite?

sowjanya gondi
Contributor
May 21, 2020

sorry. I accidentally posted the question as answer. not able to delete the post.

Suggest an answer