Can somebody please help me with this?
I am trying to set the Due Date Field to a certain date but it's not working on the issues where due date already exists. Is there a way to set the desired date regardless of prior value? overwrite?
I am using the smart Value {{issue.Sprint.endDate.jiraDate}} for Due Date field.
Hi @sowjanya gondi - Can you give us more information as to what is not working?
Can you share a screenshot of the Audit log for when you run it?
Hi John, Thank you for responding. I corrected a couple of things and the rule started working now.
1. Cleared the pre-existing value in the date field before populating it with a new date. For this step, there was reference available here in Atlassian community
2. Used smart value {{now.plusBusinessDays(10)}} instead of {{issue.Sprint.endDate.jiraDate}}
I am ok now. Thank you.
.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Can somebody please help me with this? Is the question not clear?
I am trying to set the Due Date Field to a certain date but it's not working on the issues where due date already exists. Is there a way to set the desired date regardless of prior value? overwrite?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sorry. I accidentally posted the question as answer. not able to delete the post.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.