First let me explain on left side is folder with tasks, that goes the percentage of completition, and sum of story points.
If i have divided tasks to folders and have percentage, can someone explain to me,
what this image shows?
That tasks in "add new campaign step 1" are finished 82%?
If yes that it basically means that there are 184 from 1022 Story Points left
image2016-5-6 18:18:41.png
BUT
When i exclude tasks that are completed i get that there is 471 Story Points left
image2016-5-6 18:13:51.pngimage2016-5-6 18:18:48.png
The problem was that i haven't set the weight to story points.
Thanks for confirming!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Davor,
Eugene from ALM Works here. Could you please send the screenshot of the progress column settings to support@almworks.com or open a ticket at jira.almworks.com.
There are a few additional options there that affect how the progress is calculated.
It's hard to say why you have these values without seeing these options.
Thanks,
Eugene
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.