Hello JIRA Community,
Currently, I have Project A and Project B. I have 2 automation rules set - 1 that allows me to clone tickets from Project A to Project B when a specific assignee is chosen, and 1 that automatically updates the due dates of cloned/cloned by issues so that they are in sync.
The first rule works perfectly, however, the problem lies in when I try to sync the due dates of a specific task that has been cloned from Project A -> Project B.
To clarify, I've mapped out the steps.
(->) The arrow represents an automation rule taking place. I am having trouble with the underlined part. The cloned ticket does not sync due date with the original ticket. Below is the automation rule I've attempted but with no luck:
Hi @Yenni Giang
What do you observe happening when the due date is changed?
Please post images of:
As this rule is trying to access and update issues in multiple projects, the rule's scope must be multi-project or global.
Kind regards,
Bill
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.