Hi,

I am new to JIRA. I need to perform an upgrade from jira core 5.2.7 to 7.10. Someone please let me know on how I should start with. Appreciate your help on it. Thanks in advance.

2 answers

1 vote
Yogesh Mude
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 27, 2018
Andy Heinzer
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 27, 2018

You can't do this in a single upgrade.  You are going to need to upgrade to at least one intermediate version first (a 7.0.x version).

I would recommend that you use the Upgrading Jira with a fallback method.  This method might take some more time to complete, but it offers the best means to make sure your data is properly upgraded and users suffer the least amount of downtime possible.

0 votes
Sumitra Vishwanath June 27, 2018

we have an apache tomcat installed with jira core. Why apache tomcat is used? 

Andy Heinzer
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
June 27, 2018

Jira is a Java based program.  Since Jira needs an application to host its website, it makes sense that Atlassian uses Tomcat since this too an a Java based webserver.