There are several ways how to get planned tasks according to the method of how you mark those planned tasks in Jira. Is it some date field or status?
If planned issues are unresolve issues with some planned resolution date, like “Due date”. Then you may use measure “Issues with due date” together with dimension "Resolution", and select resolution (unresolved). To get a report only on tasks, use dimension "Issue Type" on pages.
If planned issues are issues in a special status, then you may use measure “Issues created” together with dimension "Status", and select statuses of interest. To get a report only on tasks, use dimension "Issue Type" on pages.
You may also represent the same results as calculated measures using a tuple of measure and dimensions. For more details on calculated measures and tuples, see the eazyBI documentation: https://docs.eazybi.com/eazybijira/analyze-and-visualize/calculated-measures-and-members/calculated-measures.
You may also start by checking out some examples of due issues in eazyBI Demo account: https://eazybi.com/accounts/1000/dashboards/4553-jira-issues.
Best,
Zane / support@eazyBI.com
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.