I am trying to resource planning on Big Picture. I need to allocate different work hours on different days for a resource. Let me explain using an example. Say at Ticket TKT-1010 is assigned to Mr.X with the following estimate
start date 14th Feb, 2019
end date: 20th Feb 2019,
Original Estimate - 24h
So, Big Picture will allocate 6h each day form 14th Feb to 20th Feb. However, in our scenario, the resource has to work
Can this be achieved using big picture resource planning? If not, is there a work around?
Hi,
We are working on this functionality.
Firstly, we are planning to release ONE-21129 - users will be able to select a front- or back-loaded workload contouring mode so that a task effort could be distributed starting from the beginning or starting from the end of the task duration.
In the next phase, we will release ONE-2841 - a manually configurable workload.
In case of having trouble accessing the link, you may try Incognito.
Cheers,
Patryk
Thanks for your response, Patryk.
Could you please let me know a tentative timeline by when you plan to release this feature for the cloud version?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
👋 @Sudheer Reddy RFloat is a resource management tool that enables you to manage your team with this granularity of work days, hours, and availability一 and they've just launched an integration with Jira! You can check out the listing on Atlassian Marketplace here.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.