In Scheduled Emailed Report how can I add the date of last activity

Patty Phifer
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 4, 2024

I am working on sending an email with a generated report.  I have been able to pull together all the other information I need except the dateLastActivity .  I am not sure how to capture that in the report.  Below is my report information and email... 

{cardname} ({cardlink}) ({cardmemberusernames}) {{%Assigned to:}}\n\n

 

I tried using {{%dateLastActivity}}  

 

any help would be appreciated.

trello automation.PNG

1 answer

1 accepted

1 vote
Answer accepted
Stefan Salzl
Community Champion
March 4, 2024

Hi @Patty Phifer 

Acoording to the link

https://support.atlassian.com/trello/docs/butler-variables/

 

it should be:

{cardlastactivitydate}

 

Best
Stefan

 

 