I saw this question pop up a couple of times on the board, but didn't find an answer that suited my specific question.
I have an automation set that a checklist will be added to a card once that card is added to a specific list.
The card will arrive on that list already with a due date so I would like to generate due dates on the checklist item based on the due date of the card.
example due date card is = 31/10/21
checklist item 1 = due date card -6W
checklist item 2 = due date card -4W
Is this possible? I can't seem to find it in the automations.
There is an option to set it based on a CF date with some increment/decrement of periods like days, weeks, months...etc but it does not support the kind of setting the way you have described. The only way I found to do this kind is via http request to an endpoint.
Thanks for the quick response. I will check with our developers to see whats possible
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, you probably need to enlist their help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@milynnus How do i set the dates on a checklist to be based on a CF date? What does CF stand for?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Krystal Bella CF stands for custom field.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.