Hi,
I want to send a custom E-Mail notification when a certain checklist item is completed. Within the E-Mail, I want to mention the date two weeks from the date the checklist item is marked as complete.
Is there a way to access the date like {date} and add two weeks to the current date?
Thank you very much in advance!
Best
Hi @Julian Stang and welcome to the community,
Outside of the box, trello offers these automation variables https://support.atlassian.com/trello/docs/butler-variables/ in which there isn't any direct reference to the date of the checklist. So I would assume that out of the box you can't do that. In jira there is the lookup component to look for issues (card) under certain criteria. I would try to find a powerup to do this kind of automation.
Thank you for the fast answer!
I just want to use the {date} variable but add 14 days to it within an E-Mail, is that possible?
Best
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Or if you want working days then {date+14wd}
Read more here https://support.atlassian.com/trello/docs/arithmetic-and-formatting-in-date-variables/
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.