I would like a group to receive an email 1 week after an issue transitions to a particular state.
So far I have managed to set this up but without the 1 week delay.
Hello, let me give you some hints:
Thank you.
I did the following and it worked:
When Issue transitioned to (my status)
If: Issue Matches JQL:
project = (my project) AND status = "my status" AND status CHANGED TO "Despatched" BEFORE -7d
Then: Send email