I have several boards in my JIRA project, and I specifically modified the settings of each board to show tasks completed not later than 2weeks. However, that doesn't seem to work any longer. It worked for a long time, and just last week I started seeing tasks completed very long ago (as far back as 2020, 2021 and 2022). I like to keep the board neat and organized. Any suggestions on what to do? I have modified the settings to even show tasks that were completed not later than 1 week, but to no avail, Please help!
I've always found this to be related to the fact that it is using Updated in conjunction with Status category = Done to decide what is hidden and when.
So, if someone adds a comment, changes a field value on a long closed and hidden issue, it will reappear on a Kanban board as long as it still meets the filter query criteria as it has been Updated within the last 7/14/28 days.
Have you checked the history? We have recently been experiencing really old tickets being transitioned by an anonymous user, that no-one can explain. Maybe this could be why?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What are the board filter and sub-filter for completed?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.