I am aware of how to hide tasks with JQL on boards, however I would like to hide completed tasks when looking at an individual work item, creating a cleaner visual when reviewing items that might have 50+ attached subtasks. Any ideas or workarounds would be greatly appreciated, thank you.
Hi @Josh Drake ~ you can do this....click the ellipses in the Child work items table and check the "Hide done" box... this also works for sub-tasks. HTH!
@Josh Drake there is not a way to do that with the delivered functionality at the work item level. There are also not any apps that I am aware of that provide that functionality.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Laurie Sciutti Thanks for correcting me. I have voted for your answer.
@Josh Drake does not look like there is anything available for linked work items.