How to limit Original Estimate for subtask for 4 hours in Jira Server?

Rinjini Poddar August 9, 2022

I want to limit the Original Estimate for Sub-task to 4 hours in Jira Server.
How can we do that?

Can anyone give me solution for this?

1 answer

0 votes
Joseph Chung Yin
Community Champion
August 9, 2022

@Rinjini Poddar -

Welcome to the community.  Unfortunately, it is not possible to limit on what users enter in against the Original Estimate field systematically.  The only way that you can achieve it is through business process training of your users.

Best, Joseph Chung Yin

Jira/JSM Functional Lead, Global Infrastructure Applications Team

Viasat Inc.

Rinjini Poddar August 9, 2022

Can you give me the alternative solution for this?

Joseph Chung Yin
Community Champion
August 9, 2022

@Rinjini Poddar -

For business process training of your users is simply notifying them that when entering Original Estimate time of your rule "Nothing greater 4 hours".

Best, Joseph