Is it possible to automatically capture the date when the status of an issue in a project changes, such as from "TO DO" to the "Planning" phase, and then store this date in a custom field?
I would like to have it for the whole path for the issue, maybe some of you guys know how to do it :)
Best regards,
Vladimir
Hi, Vladimir! How are you?!
Yes, it is possible. You need set a value on field that you neet copy the date. And you can do this on Automation. (I used Due date)
To manipulate the date with something, you can use date smart values. Like that:
Hope this helped you!