In the WBS Gantt, is it possible to set the tasks by myself instead of insert the tasks from a project or a filter? Eg. there is a task belongs to a project, but I don't want it to be shown in the Gantt. I try to delete it from the Gantt but seems like it has to be deleted completely.
In the WBS Gantt, is it possible to set the tasks by myself instead of insert the tasks from a project or a filter? Eg. there is a task belongs to a project, but I don't want it to be shown in the Gantt. I try to delete it from the Gantt but seems like it has to be deleted completely.
I understand your concern.
You have no choice but to select from either a project or filter in order to create a Gantt.
The best way I can think of to fulfill your requirement is to create a Gantt by selecting a filter.
You can use Save your search as a filter feature or an advanced search such as JQL that can be helpful to hide your issues/tasks from the WBS Gantt-Chart.
Below are the steps you will need to take to set up a filter/JQL.
Basic Search - Save as a filter
Click Filters > Select Advanced issue search
Once you define and run your search and then save it as a filter, you can create a new Gantt from the saved filter.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.