I would like to move a Story with its sub-tasks to another project. I see the move option for the Story, but how would I move the sub-tasks along with it? Would I need to move the sub-tasks individually to the new project and assign them back to the Story individually?
We are using Jira Data Center version 9.4.14.
Hi Bill.
You may find answer your question in the documentation below:
- If your issue has sub-tasks, the Move issue wizard will also move the sub-tasks to the target project.
Regards,
Vicknesh [ServiceRocket]