Running a software project and I want Front End and Platform time estimates to be separate on each ticket. 

Ideally I want this to work like the Original Estimate field and also show individual Time Tracking for both FE and Platform against those estimates.

I think there might be a way to do this via custom fields but I'm not sure exactly what I need to do or if it's actually possible?

2 answers

1 vote
Yuliia Hushcha _Reliex_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 2, 2024

Hi @Victoria Brewster 

Do you use any add-ons for Jira?

You can add work log categories in ActivityTimeline and see in the reports how much time was logged for Front End and Platform. 

You will enjoy the as well our intuitive drag-and-drop feature, while holding the 'Shift' button, effortlessly splits tasks among assignees. 

Multiple Assignees for a Single Task

 

Should you have additional inquiries, feel free to contact us. We would be delighted to provide you with a free demo session if you find it valuable.

 

0 votes
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 2, 2024

Hi @Victoria Brewster 

Welcome to the community

You can create sub-tasks for frontend, backend, design and assign them separate time estimates.  Time estimates roll up to the parent (story/task/bug).

With custom fields this might be possible, but you would also need to create automations for any changes on logged time (subtract to show remaining time), changing the original estimate, etc...

Also this will not be taken into account into the default Jira reporting on a project.

Jack Brickey
Community Champion
February 2, 2024

Also consider using Components for your SW subsystems. I prefer this as I can more easily report on the subsystems.