New Calendar cannot be reported on in Reports

Elaine McMillan
Contributor
November 29, 2021

The new calendar is great but the Planned Start and Planned End Date/Time cannot be used as a series for reports which is annoying as only Creation and Resolution dates can be used which is ineffective for Change reporting. Is it possible to amend the reporting series options to get around this limitation?

1 answer

2 votes
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 30, 2021

Hello @Elaine McMillan,

Thank you for reaching out to the Atlassian Community!

When it comes to Service Management reports, currently, it’s not possible to create custom series. 

There is a feature request suggesting improvements for that:

Please, click on vote and also watch the ticket above to receive updates.

The workaround, for now, is to use gadgets on the dashboards or add-ons:

Kind regards,
Angélica

Elaine McMillan
Contributor
December 1, 2021

Thank you for the reply. I am aware of the request to be able to customise the series selection. The Change issue type is a specific use case as Atlassian have released a calendar that requires use of the Planned Start and End Dates but without joining the dots to the fact that system users will need to be able to report on these fields.  