srikanth_rao April 29, 2025

Hello Community,

I am trying to make the time tracking field available in a project and I have made sure that the field is added to the screen configuration and also ensured it is added to the layout as well, despite making sure all required steps are done I am still not able to see that field. Can someone please help me on how I can make sure the field is displayed?

My project is showing the Original Estimate and Remaining Time fields, I have made sure both of these have the value but still the time tracking field does not show up.

1 answer

2 votes
Marc - Devoteam
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 29, 2025

Hi @srikanth_rao 

You need to log work.

And Time Tracking is not a field, but an option.

Fields related to time tracking are Original Estimate and Remaining Time.