Hi All,
We have a process where when an issue is logged by a customer which requires a software patch, we raise a ticket with the developers project and link the two tickets.
We are trying to see if there is a way to automate the creation of internal notes in the parent ticket whenever a status has changed in the linked developers ticket.
Basically to say something like DEV-123 has transitioned from TRIAGE to UAT TESTING or whatever the status is.
George
Hi @George Abdo !
You can achieve that through an Automation like the following:
You can either use the Linked issue branching, or the parent issue.
From the scenario you said, I think the Linked Issue will work.
Thanks @Vando Goncalves _e-Core_
I will test this in our sandbox environment. It looks like the logical process.
I'll confirm if it works as expected.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.