Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Automation rule NO ACTIONS PERFORMED

Petr AST
Contributor
October 8, 2020

Hi dear community!
Faced a little question:
After setting up and fully using automatic rules, it turned out that their implementation was limited.
This strained quite a lot, because the whole business process is built on this:(

There is a rule that is triggered after adding a comment. Then there are two conditions, in most cases these conditions do not pass and the rule ends with the status NO ACTIONS PERFORMED.

However, it counts as completion and the limit is reduced. Did anyone manage to set it up so that the limit decreases only from the successful execution of the rule?

Thanks a lot!!

Screenshot_16.png

1 answer

0 votes
Dirk Ronsmans
Community Champion
October 9, 2020

Hi @Petr AST

I understand that this can be frustrating that you only want the rule to count towards your limit when an action has been performed.
However from an Atlassian point of view the rule was executed as it was evaluated fully (it was triggered) but it turned out that there was no action needed.

So this does count towards an execution of the rule.

You can always evaluate whether your trigger can be set less broad so it triggers less.

Another one however is to move the rules from "Global/Multi project rules" in to project specific rules.

Normally project specific rules have no execution limits where as Global rules do based on your tier and number of users.

https://support.atlassian.com/jira-software-cloud/docs/how-is-my-usage-calculated/ 

Petr AST
Contributor
October 9, 2020

Hello @Dirk Ronsmans  

I completely understand your answer. But when a comment is added, there are no other options. Translation of a rule for one project does not affect linked tasks, which in this case will not help automate the process in any way.
From my position, it would be convenient to add several triggers, for example, the "add comment" trigger and immediately the trigger condition. 

And of course avoid " no actions performed " in the limit counter

Dirk Ronsmans
Community Champion
October 9, 2020

@Petr AST ,

Are you sure that you cannot translate them to single project rules?

As far as i know a single project rule can still interact with other projects/linked issues but the condition is only triggered/monitored for that single project.

Or I misunderstood how you rule is set up :)

Petr AST
Contributor
October 9, 2020

@Dirk Ronsmans  No, that doesn't work.
For example, the rule starts every 5 minutes, if there are clones that are done, then add a comment. Very simple example, but it should work. No. Nothing for single project. But if we change amount of projects to 2 - this rule work exсellent. 

Screenshot_18.png

Maybe I'm wrong, but so far I have not been able to achieve at least some result using one project.

Dirk Ronsmans
Community Champion
October 9, 2020

I feel like this has be possible with less :)

So if I understand correctly, you want the automation to:

  • Run through all the issues in project "TEST" that are != Resolved
  • Then if those tickets have a Clone with Status = "Done"
  • Put a comment in the original issue or the clone?
    • (i would guess the original one where you says something like "clone x was done"?)
Like Simmo likes this
Petr AST
Contributor
October 9, 2020

@Dirk Ronsmans 

No, this automation is for an example that if we do not have multiple projects connected, we cannot search for linked tasks. 

Simmo
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
October 12, 2020

Hi @Dirk Ronsmans & @Petr AST ,

I'm not sure quite what the actual use case is here but if this is based on transitions, it might make more sense to use the issue transitioned trigger. You can filter on that trigger to the destination status that you want.

So, in this case, if a ticket is transitioned to Done, go through its linked issues, etc.

Cheers,

Simeon.

Like Petr AST likes this
Petr AST
Contributor
October 13, 2020

@Simmo  Hi Simeon! 

The original question was that the trigger fires on every comment, checks the conditions, not finding the desired condition, completes, but the counter also increases.


Instead of one rule, I ended up making 4 rules based on field changes in order to minimize automation for many projects.


And the second question, which we also considered here, is that if the automation is only for one project, it cannot check related applications from other projects.

Automation with status transitions is already configured, thanks:)

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events