I have set up some SLA's and all are running with a 18/7 calendar.
For low impact tickets we have 21 days to resolve.
In order for this to calculate correctly which is below hours should I use.
21 days X 24 hours = 504h
Or
21 days X 18 hours = 378h
Thanks a lot.
Theis
Hi @Theis Joergensen ,
If by an 18/7 calendar you mean that there are 18 working hours in a working day, then you should choose your second option.
During non-working hours, your SLA timer is paused. So don't include your non-working hours in the calculation.
Hope this helps!
Thanks, it surely helps.
Our calendar is 06.00-24.00 CET all 7 days of the week so I will go with my second option.
Brgds
Theis