BigGantt does a great job of showing THE critical path, but is there a way or feature to show other tasks that are close to the critical path?
Hi I'm using Biggantt app. I'm trying to implement the baseline feature, however, it does not seem to map to the Gantt chart. I thought it should be the Baseline End Date field, but the b...
I have a project set up in BigGantt. The project tasks have been imported successfully, I have been able to map the custom fields of my project, including the start date and end date, etc., e...
Hello, My team wants to utilize the BigGantt app offered by Appfire - BigGantt - Gantt Chart for Jira | Atlassian Marketplace Some of the research I have been doing suggests that I would a...