Hello, I noticed this, go to your overall Backlog check the priority of the Initiatives (for example), filter on a Team then check the priority again, Portfolio changes the priority of certa...
in building a portfolio plan many of my stories are assigned to epics, but some are not. is it a best practice to assign all stories to epics for effective scheduling in JIRA Portfolio?
I would like to know why some tasks for an Epic does not show up in Portfolio. For example, in the attached screen shot #70 Epic AP-81, there are many more tasks under the epic but they don't s...
Hey there, we used Jira and Portfolio only for our company and everything was fine. Now we start a new project with an new client. We want to let him into our JIRA System. He should see only one proj...
This morning I took Portfolio for Jira from the Marketplace. In the header I cannot go beyond 'settings'. Besides I cannot find it under the add-ons unless I select 'system' add-ons. If I do th...
When I try to delete a plan from Portfolio the app shows a message confirming but never ends and it's impossible to know why? How Can I see the problem? I've tried deleting first all issues f...
Hi, I want to show the target schedule view in Portfolio based on a custom field value. Is this functionality available? If not, any plans to have this in a future release? JIRA v7.8 Portfolio v2...
Browsing javadocs for rest api, I saw interfaces entries (LINK) about plans and related stuff. I am intersted in using some of these, but I cannot find any documentation about usage... ...
we realized that the progress bar is turning green in 2 cases: 1. When the tickets are resolved (seems right) 2. When the original estimate matches the actual estimate hours ( this seems wrong) bec...
I'm getting this warning on an issue, but I've triple-checked the currently assigned team member is in the plan and he actually has other issues assigned to him within the same team. Nothing se...
What is the best way to manage dependencies between releases (e.g. fixVersions). In JIRA FixVersion A 2.1 has a dependency on another application B 2.0. Meaning, A 2.1 cannot be deployed to productio...
Here is the scenario - I created an Initiative. - Created two epics with Initiative - Created two stories with one of the epic - Assigned a release with a fixed release date (31-July-18) - ...
Is there any way to create Releases in Portfolio automatically ? (by using API or something..._
Hi, do you have any idea when the Portfolio plugin for Jira will be released in a version compatible with Jira server 7.10?
I generally see my roadmap by stories. When a Story is finished, it disappear from portfolio and I cant show them, for example, on a status report showing it is 100% finished. Right? Is that be...
I need to turn off Portfolio's automatic sprint generation until I can find sufficient documentation to be able to control it. I'm getting projects and teams that show between 20 and 50 sprints ...
I excluded a few issues from my JIRA portfolio plan, and now I'm realizing that I want to pull a couple of them back in. I searched online and found that some people have had success with using the C...
The documentation refers to the ability to update a Plan from Jira by using "Update from date" and to configure synchronization. Neither of these are anywhere in my Plan that I can see. Where should ...
Hello, following simple scenario: One newly created Project and (Scrum)Board and no sprints started. I have one Version, one Epic and three USs each of them assigned to that Version and Epic. Each U...
I am trying to create multiple issues through my post function. I would like to assign teams for these issues through the transition screen.I am using nFeed add-on to fetch the team title and team ID...
Hi Portfolio Users, I want to create a plan for a project, of which no issue is estimated with story points and there is no release planned yet. I tried the default estimations for epic, story and in...
My results from the JQL filter is correct but after creating the plan, setting the More > Statuses to show all available, some issues are not showing in the Scope grid. No other plan filter a...
I am using JIRA portfolio and I am using Themes. When I look at the theme report is says that a certain percentage in the estimate pie chart and actual pie chart has no theme assigned. Any what cause...
Hello Team, We tried creating Plan using the board and we noticed teams are automatically created. We need to understand how does these teams gets created ? For example: &nb...
When I try to create a plan in Jira Portfolio, Portfolio seems to pay no attention at all to the existing (and past) sprints for my project(s). It assigns issues that are already in an active sprint ...