×I'm trying to trigger a Custom field in the Jira Portfolio scenario. This custom field is based on a script that has been created in the ScriptRunner, Fields sub-tab. Thanks in advance.
Is there a means of representing a "Finish-to-Finish" dependency in AR? Right now all I seem to see is the "Blocks" dependency which seems to be aligned with a "Finish-to-Start" perspectiv...
I want to be able see a list of all Due date changes in the past week. I have an updatedDate JQL but i believe this gives me a list of all issues that have had any changes made rather than specifical...
as you can see in image i am able to view all the issues with the all status except PBYA-12 which is in "UAT-Approved" status may i know what's the reason?
Our current Hierarchy structure consists of Initiative --> Capability --> Epic --> Story where each Initiative is a large effort that spans many PIs/Years. We are having great success ...
When trying to select the Releases for a Plan, our Releases are all out of order by name and start/stop dates which is really annoying when trying to find the handful that you need for the specific p...
While struggling with issues not showing up in Advanced Roadmaps like several other users, I have finally noticed that sprints assigned to issues seem to not be handled exactly the same way between J...
I have created plan and in plan configuration selected the specific releases in "issue sources" from the boards that should be included but this is not working. In The releases tab - i have selected ...
We have an Advanced Roadmaps Plan which is working fine. All the data, also custom fields, are shown as it should be. When I perform an csv export via the dedicated button on the top, I get a csv fil...
Are "we" crazy/alone for having a requirement of Cross Project Releases in AR to be able to add more than one release from one project into a Cross Project Release? i.e. Project A has Release 1.9 &...
I'm starting to roll out Advanced Roadmaps in our organisation. It's a relatively mature Jira instance so it has a number of custom fields for start/end dates depending on the context. Are there any...
I've just noticed the Dependency style option in "view settings" (FYI - am trialing the new header style...in case that matters) But changing it to Lines from Badges doesn't seem to make any differen...
Currently if you make a shared team in Advance Roadmaps it shows up in every project in JIRA, which is painful since the teams are not sorted and you have dozens of teams. Is there any way t...
I have created 2 custom field date fields (baseline date and due date) I have also created a third custom numeric field called variance. How can I get the following result baseline date - 15 Apr 2...
When I select my plan I am receiving this warning and am not quite sure what it means. "Plan contains team-managed projects". My guess it is telling me it doesn't support Next Gen projects and one of...
Can I custom sort my projects in the advanced roadmap? It wont let me drag and drop custom sort them like you can with issues. Or how can I sort them by either start or due date?&nb...
Hi, I'm concerned about potentially impacting an existing Parent Link (Epic Link in this case) of an issue without realizing it due to Review Changes screen not reporting a pending change. The scena...
We are unable to rely on projected sprint calculations, it keeps showing subtasks as unestimated issues. As part of our practice, we don't estimate subtasks, we estimate only stories and epics. Is th...
We are using Jira Data Center version 7.13 and Advanced Roadmaps. We want to introduce Safe Hierarchy. Theme--> Epic -->Capability --> Feature --> Story Finally we want to start cr...
We are running Advanced Roadmaps version 3.28.0. My plan has 1 project with 54 issues. When reviewing changes, we are experiencing performance issues. It took 90 seconds to commit 12 changes. On my...
Hello I am setting a plan in Roadmaps, but the number of days showing on the plan is inaccurate as it is taking into account weekends. I am in the configuration of the plan in the redesigned planni...
Dear Community, We've been preparing metrics in a manual way via excell files (we've five scrum teams working on a single programme). These metrics shows the predictions when particular scope ...
Hello, I have seen in Jira blogs how roadmaps can be configured to show icons for different initiatives helping to break up the roadmap sections and make them easier to visually scan. I ...
Hello! When we create a new issue of the "Story" level in a plan we don't understand which is the default issue type. In our case the plan creates a bug issue by default...
I am curious if you remove issues from a plan that have remaining estimates and a Team assigned, will team capacity free up? Or will these removed issues still count against capacity?